Saint Mary Bikelane Update

As you may have noticed, the Saint Mary bikelane has had no progress in the time between when it was announced and now. This is because the paint used for lane markings needs to be applied when the temperature is 50 degrees. We are told that it will probably 3-4 days of work so we may be waiting a little while but it is happening.